MRP theory

 0    7 fiche    dklekowski
laste ned mp3 Skriv ut spille sjekk deg selv
 
spørsmålet English svaret English
bull-whip effect
begynn å lære
small order changes in downstream demand lead to large upstream variation -> high unwanted inventories
lumpy demand effect
begynn å lære
Rip systems not first for unexpected, high demands
unreliability effect
begynn å lære
FG product consists of 5 parts, each of availability of 95%, then FG availability 77%
BOM
begynn å lære
bills of material
special BOMs
begynn å lære
modular bills, planning bills, phantom bills (used for subassies that exist temporarily
MRP requirements
begynn å lære
computer system necessary, mainly discrete products, accurate bill-of-material, accurate inventory status, stable lead time, problem with frequent re-planning
Four periods in the Rolling MPS
begynn å lære
Frozen - until week 4, new orders cannot enter and we can't change them; Firm - orders confirmed by customers; Full - we can shift things; Open - we can still assemble orders, we don't have to plan yet