Short-time scheduling

 0    16 fiche    dklekowski
laste ned mp3 Skriv ut spille sjekk deg selv
 
spørsmålet English svaret English
Types of short-term scheduling
begynn å lære
Forward scheduling and backward scheduling
Forward scheduling
begynn å lære
begins the schedule as soon as the requirements are known; often builds up WIP; jobs performed to customer order, schedule can be accomplished even if due date is missed
Backward Scheduling
begynn å lære
begins with the due date of the final operation, schedules jobs in reverse order, used in many manufacturing environments; ex. catering
Goals of short-term scheduling
begynn å lære
minimize completion time, maximise utilisation, minimise WIP inventory, minimise customer wait time
process-focused work centres
begynn å lære
high variety, low volume, mate-to-order, different materials and processing for each product, complex production planning and control, production scheduling aspects
Loading Jobs in Work Centres
begynn å lære
assigning jobs to work centres; approaches: input-output control, Gantt charts, assignment method
Input-output control
begynn å lære
CONWIP - constant WIP; for given average output rate, try to keep L low and constant then W will be short and constant; Little's formula
Gantt Load chart
begynn å lære
shows relative workload in facility, negatives: does not account for unexpected events, must be updated regularly
Assignment Method
begynn å lære
occurs in many environments: resources-jobs, planes-gates, course-rooms); type of binary linear programming model
Priority rules for Dispatching Jobs (sequencing)
begynn å lære
FCFS, EDD, SPT, LPT, CR
FCFS
begynn å lære
First come first serve; the first job to arrive at a work centre is processed first
EDD
begynn å lære
earliest due date; the job with the easiest due date is processed first
SPT
begynn å lære
shortest processing time first
LPT
begynn å lære
longets processing time first
CR
begynn å lære
critical ratio; the ratio of time remaining to required work time remaining is calculated and jobs are schedules in order of increasing ratio; CR = time remaining/work days remaining -> process jobs with the smallest CR first
Criteria to evaluate priority rules
begynn å lære
Average Completion Time= Sum of flow times / # jobs; Utilisation = Sum process time / sum flow time; Average number of jobs in system Sum Flow time /Sum processing time; average jobs lateness = sum late times / number of jobs